Gisborne District Council TechnologyOne upgrade years behind schedule

An 18-month technology upgrade for Gisborne District Council has dragged on for almost five years, with $8.1 million spent and work still incomplete.
The council began procuring the technology upgrade in 2021 to modernise systems used to deliver services, manage information and support day-to-day operations.
According to information released under the Local Government Official Information and Meetings Act (LGOIMA), the multiyear programme was intended to strengthen business continuity, reduce manual processes and improve information management.
A contract was awarded to TechnologyOne in February 2022 to replace the council’s existing Enterprise Resource Planning (ERP) platform and Ozone, which was due to be discontinued by its vendor.
At the time, council director of internal partnerships James Baty said the existing technology did not always “talk to each other seamlessly”, making it difficult to access accurate, real-time information for decision-making.
“We also have information stored in a variety of systems and places, and that increases compliance costs and risk.”
TechnologyOne said its cloud-based software would be introduced in stages across the council’s finance and budgeting, procurement, human resources and payroll systems.
The programme was initially expected to take 18 months, but is now 57 months from the start of procurement.
Timeframes were revised because system configuration, data migration and business processes required more time and resources than anticipated, the LGOIMA response said.
In March 2024, the council issued a tender for a delivery partner to migrate 2.5 million records from its legacy Enterprise Content Management System to TechnologyOne.
The LGOIMA response said this work formed part of the broader TechnologyOne programme.
Two positions have since been advertised on Seek to support the implementation, the latest in October.
One was a project and training support officer to help deliver the Enterprise Solutions Programme and support staff adoption of TechnologyOne.
The October advertisement was for a fixed-term, two-year data and business analyst role supporting the ERP implementation.
The LGOIMA explained the two positions were established to support data migration of legacy systems, expected to take two years.
The roles would provide dedicated resource capacity for “a significant phase of the programme’s data migration activities”.
Five workstreams, including financial, procurement and supply chain, and contract management, were successfully implemented within TechnologyOne.
However, seven remained outstanding, including property and rating, regulatory and compliance, and customer portals and online services.
“These remaining workstreams represent some of council’s most complex business functions and require detailed business process design, configuration, integration, data migration, testing, staff training and compliance validation before they can be implemented,” the LGOIMA response said.
The LGOIMA said staged delivery would ensure services remained available while new systems were implemented safely and effectively.
The programme was expected to have minimal direct impact on businesses, as most change would take place behind the scenes.
Any expected impacts would be communicated to stakeholders in advance.
A TechnologyOne spokesperson said the company had worked closely with the council throughout the implementation and remained committed to completing the work.
“The programme has taken longer than planned as requirements and priorities have been refined with the council.
“Large council programmes are delivered in stages, and timelines can change as the work progresses. Our shared focus with the council is getting the transition right for council staff and the Gisborne community.”
The budget for the project from 2022 to 2026 was $9 million; $8.1m had been spent to date.
A council spokesperson said the 2021-2031 Long Term Plan, which was replaced by a three-year recovery plan after Cyclone Gabrielle, included an initial estimate of $4.5m for the Enterprise Solutions project.
That covered the 2021/22 and 2022/23 financial years.
“This amount was set aside in anticipation of the existing system becoming unsupported, and before council had undertaken detailed scoping or confirmed the requirements and costs of its replacement.
“The $9 million budget for 2022–2026 reflects subsequent estimates approved through council’s Annual Plan and Long Term Plan (LTP) processes as the programme’s scope and complexity became clearer.”
The approved budget for the 2026/27 financial year was $3.5m.
Budgets for subsequent years had not been approved and would be considered through the council’s 2027 to 2037 LTP process, the spokesperson said.
The council expected to adopt the new LTP in June 2027.
LDR is local body journalism co-funded by RNZ and NZ On Air.
